Saturday, December 22, 2007

Long overdue update

The weekend following the foundation pour, we laid the sewer and water as well as finishing the driveway in front of the slab. We rented a trencher and a tracked skid steer loader for the job. Other than a minor few problems (getting the plug out of the sewer line, no tripod for the laser rental) things went pretty good.

Power is still an estimated 2 months out. Hopefully it comes sooner. It wound up costing us much more than we anticipated to get this installed. Centerpoint has some absurd demands and requirements.

Most all of the steel has been delivered and we have started fabrication of the columns. We currently have all 6 of the two story columns ready to go, but only 1 of them up. Also, we have 4 single story columns set. I have neglected taking any pics of this yet....
More to come soon...