Monday, March 17, 2008

Structural Frame

Complete! We started fabrication on 12-15-07 and completely finished the structural steel on 3-16-08. Here is the finished frame. Today we also got the water tied in...hopefully no leaks!























Saturday, March 15, 2008

Day 4

All but 2 beams.







Friday, March 14, 2008

Day 3

I know...I skipped a day. Things have gone fairly well the past few days. Only 11 more beams remain!









Wednesday, March 12, 2008

Second Floor - Day 1

After a bit of trouble getting the manlift back to the house we finally have begun.




Sunday, March 02, 2008

Power!

The much needed and overdue electric pedestal is installed! The meter *should* be set March 5th. The first floor and second floor columns are all up. We are working on all the second floor beams. Should have them done by next weekend and ready to go up.